- Community
-
- About Sherwood Sherwood Heritage Center Chamber of Commerce Marjorie Stewart Center Sherwood Center for the Arts Sherwood YMCA Family Resources
- Events and Activities City Calendar Library Events Community Events Event Permits Monument Posting Request Community Meeting Rooms Recreation Parks and Trails Directory Recreation Programs Sherwood Fieldhouse
- Community Field House Sherwood Demographics Sherwood School District Sherwood Youth Sports Utilities Volunteer Opportunities Highway 99 Pedestrian Crossing Public Safety Police Tualatin Valley Fire & Rescue
-
- Business & Development
- Government
-
- City Council Boards and Committees Urban Renewal Agency Agendas and Minutes Municipal Code Public Records
- Building City Attorney City Manager Code Compliance Community Development Community Services Economic Development Emergency Management Engineering
- Finance Human Resources Library Municipal Court Parks & Recreation Planning Police Public Works Utility Billing
-
- Online Services
-
- Job Opportunities Utility Billing Alerts & Notifications Email Subscriptions Sherwood Flash Alert Police Flash Alert Events and Meetings Agendas and Minutes Calendar
- Contact the City Submit a Request or Concern City Offices Municipal Code Documents and Forms Documents and Reports Forms and Applications
- Social Media
-
Land Division -Planning Review Process
The Planning Department is the first stop. Planning looks at the whole site and coordinates with the appropriate departments and agencies to ensure the site can be developed as planned.
To get started, submit an application with all required submittal elements. It will take up to 30 days for the initial review to determine if all necessary information has been submitted.
Once all required information has been submitted, staff will deem the application complete and schedule the review. The typical review period is approximately 6-8 weeks from when your application is deemed complete. The decision will be approval, denial, or approval with conditions.
If the proposal is approved, or approved with conditions, the Notice of Decision will outline specific conditions that must be met at specific stages:
1) Grading
2) Issuance of Engineer Plans
3) Final Plat approval
4) Recording the approved Plat
5) Submittal of Building permits
6) Issuance of Building permits