Land Division -Engineering Review Process

After the appeal period for a Land Use Approval has passed you may submit your plans to the Engineering Department for review. The Notice of Decision may have required plans to be revised to address specific design conditions. The Engineering Department will not be able to accept the public improvement plans until after the land use Notice of Decision has been issued.

The Engineering Department reviews the public improvements (roads, water, sewer, and storm lines). It is the developer’s responsibility to coordinate installation of other utilities.

The Engineering Department review period takes approximately 6-8 weeks, but varies depending on the completeness of the plans and the number of other projects in for review. Once the Engineering Department has approved the public improvement plans, the applicant must sign a Compliance Agreement, post bonds and schedule a pre-construction meeting.

An Engineering Permit Packet can be found on the Engineering Department Home Page.