Cedar Creek Trail Construction
Cedar Creek Trail Construction

Project Stats
Project ID: 200, 200C, 200D
Project Type: Capital Improvement
Project Status: Completed
Project Location
Cedar Creek Trail Construction
Status Updates
Completed
Project Overview
The project was split into two phases in-order-to avoid federalizing the entire trail system up to SW Roy Rogers Road. Phase 1 was a design & construction project between Old Town and Highway 99W. Phase 2 was a planning project that identified a preferred alignment between Highway 99W, Edy Road, and SW Roy Rogers Road. A map of the preferred preliminary alignment for the two segments northwest of Highway 99W (99W to Edy, Edy to Roy Rogers) can be found below under the Supporting Documents section. The Cedar Creek Trail is part of the West Fork of the Ice Age Tonquin Trail.
Bid Results
- $3,846,216.72 Legacy Contracting Inc
- $4,243,116.14 HP Civil Inc
- $5,251,861.04 Corpac Construction Company
- $5,488,686.30 Brown Contracting Inc
- $3,934,907.80 (Engineer’s Estimate)
Critical completion dates:
- August 5, 2022: Sanitary sewer relocation work tested & completed.
- August 19, 2022: Two retaining walls constructed & ODOT crosswalk signal at 99W activated.
- August 26, 2022: Final paving, clean-up & contractor demobilization began.
- September 16, 2022: Substantial completion (trail open to public). Began punchlist repairs.
- October 21, 2022: Final acceptance & one-year maintenance period (completes federal fund trail project and releases City) began.
- October 22, 2022-June 30, 2023: City design & construction of local trail infrastructure & restoration of acoustic fence/visual corridor landscaping completed.
- November 14, 2024: Visual corridor & fence restoration work substantially completed.