Sunset-Timbrel Pedestrian Signal & ADA Curb Ramps
Sunset-Timbrel Pedestrian Signal & ADA Curb Ramps
Project ID: 729ST
Project Type: Capital Improvement
Project Status: Under Construction
Sunset-Timbrel Pedestrian Signal & ADA Curb Ramps
Status Updates
Under Construction
This project involves a realignment of an existing crosswalk, updating ADA ramps, installation of school and speed feedback signs, enhanced street lighting, and adding a Pedestrian Hybrid beacon.
PROJECT UPDATE (11/06/2025):
Construction for this project was paused to accommodate the delivery of the pedestrian signal equipment. Construction resumed this week for the signal pole foundations. Curb ramps are scheduled to be removed and replaced in November, pending weather conditions. Curb ramp construction is not anticipated to impact school drop off or pickup.
The pedestrian signal poles and equipment will be installed in January 2026 and commissioned in February 2026. Please check this site for construction updates and detour maps. The project is scheduled for completion in February 2026.
Project Schedule: July 14-Februray 2026.
Additional details about this project can be found in the files below. This project is also included in the 5-year Capital Improvement Plan (CIP), which can be found online here.
Get alerts any time an update on this project is made.
Welcome to the City of Sherwood’s Notification System, the city’s latest tool for providing residents with immediate information and warnings on water contamination, extreme weather warnings, unexpected road closures, etc. This is a free service provided by the City of Sherwood.