Project Status: Under Construction

  • ODOT ADA Curb Ramp Improvements, Phase 2

    ODOT ADA Curb Ramp Improvements, Phase 2

    The Oregon Department of Transportation (ODOT) is evaluating and improving more than 1,600 non-compliant sidewalk curb ramps at intersections and mid-block crossings throughout the Portland Metro and surrounding areas to bring them up to current Americans with Disabilities (ADA) standards. The project is scheduled to begin in the Sherwood area on October 13, 2025 with phase…

  • Washington St Street & Utility Improvements (Tualatin St to Division St)

    Washington St Street & Utility Improvements (Tualatin St to Division St)

    The City uses a Pavement Management System which evaluates the condition of our roadways. This year, improvements on Washington Street include: PROJECT UPDATE (07/29/2026):SW Washington St between Division and Tualatin, including the intersection of Division/Washington, will be closed for paving operations starting August 4, 2026 through August 7, 2026. Roads will be reopened overnight for…

  • Gleneagle Stormwater Treatment Facility

    Gleneagle Stormwater Treatment Facility

    This project includes reviewing the existing facility and determining corrective measures to make the facility fully operable and able to meet CWS operational requirements. Additional details about this project are included in the 5-year Capital Improvement Plan (CIP). Please see the public notification and exhibit below for more information or contact Craig Christensen, P.E., christensenc@sherwoodoregon.gov if you have…

  • Sunset-Timbrel Pedestrian Signal & ADA Curb Ramps

    Sunset-Timbrel Pedestrian Signal & ADA Curb Ramps

    CONSTRUCTION UPDATE (May 21st, 2026)THE SIGNAL HAS BEEN TURNED ON AND ACTIVATED FOR USE New Traffic Pattern Ahead signs have been placed at the approaches for advanced notice. School zone flashers are working on SW Sunset Blvd at SW Woodhaven Drive (eastbound) and east of SW Timbrel Lane (westbound).  The new school zone flasher due…

  • 2nd Street & Park Street Regional Storm Facility Rehabilitation

    2nd Street & Park Street Regional Storm Facility Rehabilitation

    PROJECT UPDATE (05/21/2026):The contractor will be mobilizing on site starting Monday, June 1st, 2026. Portions of the Stella Olsen Trail closest to the project site will be temporarily closed during construction. Due to the nature of the work, please anticipate some access delays and construction noise during construction. PROJECT INFORMATION:This project includes reviewing the existing…

  • Arrow Street Extension

    Arrow Street Extension

    In partnership with Washington County, Arrow Street will be extended on its western side to form a new intersection with Langer Farms Parkway. New storm sewer infrastructure will also be installed. Construction is anticipated to begin in Spring 2025 with completion Summer 2025. Due to the nature of the work, please anticipate some traffic delays…

  • Tualatin-Sherwood Road Widening Coordination Project with Washington County

    Tualatin-Sherwood Road Widening Coordination Project with Washington County

    This project includes widening Tualatin-Sherwood Road from Borchers Drive to Langer Farms Parkway, and on to Teton Avenue, including 5 travel lanes, bicycle lanes, sidewalks, and planter strips.  Funding is from WACO MSTIP.  WACO DLUT will be responsible for design and construction of roadway improvements as well as any maintenance responsibilities in the future. More information and status updates can be found on…

  • Brookman Sanitary Trunk Line Extension

    Brookman Sanitary Trunk Line Extension

    Please visit the Clean Water Services project webpage for more information. The trunkline will serve the future growth of the Brookman and Sherwood West annexation areas, including Sherwood High School. The line will be placed in, or near, Goose Creek and Cedar Creek, and along sections of roadways and surrounding areas. Funding will primarily be…

  • Schamburg Drive Sanitary Sewer Replacement & Upgrade

    Schamburg Drive Sanitary Sewer Replacement & Upgrade

    The public works department has identified many severe structural issues with the sanitary sewer in this area. These issues have the potential to jeopardize our ability to provide sanitary sewer service to properties.  The City has designed and bid for street, storm sewer, and sanitary sewer construction at SW Schamburg Drive and SW Division Street,…